Fuller Middle School

Client: John Turner Consulting
Project Location:
Framingham, Massachusetts
Project Size:
137,000 SF
Project Type: Air and Water Testing

Scope:

Newly constructed three-story building requiring window testing during construction to ensure that windows were installed properly and are without air leakage and water infiltration.

Services:

Window testing included a stand-alone mock-up as well as an in-building mock-up. Window testing were in accordance with the following standards:

  • ASTM E783: Standard Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors

  • AAMA 501.2: Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls, and Sloped Glazing Systems